Prarancangan Pabrik Biogas dari Limbah Sisa Makanan, Limbah Pabrik Tahu, dan Limbah Darah Rumah Potong Hewan dengan Proses Fermentasi Anaerobik Dua Tahap Kapasistas Bahan Baku 25.000 TonTahun
Preliminary Design of A Biogas Plant From Food Waste, Tofu Factory Waste, and Slaughterhouse Blood Waste Using A Two-Stage Anaerobic Fermentation Process with A Raw Material Capacity Of 25,000 Tonnes/Year Abstract
Abstract
Preliminary Plant Design: Preliminary Design of a Biogas Plant Utilizing
Food Waste, Slaughterhouse Blood Waste, and Tofu Factory Waste with a Two
Stage Anaerobic Fermentation Process and a Raw Material Capacity of 25,000
Tons/Year
This plant is designed to operate 330 days a year. The core process of this
preliminary plant design, which uses a two-stage anaerobic fermentation process,
consists of four stages: Pretreatment, Biogas Formation, Purification, and
Compression. The end product is methane with a purity of <98% at a pressure of
200 atm, resulting in bio-CNG with a production capacity of 3,441.64 tons/year and
a bio-CNG volume of 7.57 m³/kg.
The planned plant location is at the Maspion Industrial Estate, Gresik
Regency, East Java, covering a total area of 15,246 m². Water requirements for this
plant are supplied from the Kalimireng River, totaling 35,453.52 kg/hour. The
organizational structure of the planned company will be a Limited Liability
Company (PT) with a line-and-staff organizational structure, employing a total of
125 people.
Based on economic analysis, it is concluded that establishing the Biogas Plant
from Food Waste, Slaughterhouse Blood Waste, and Tofu Factory Waste with a
Two-Stage Anaerobic Fermentation Process and a Raw Material Capacity of 25,000
Tons/Year is feasible.