dc.description.abstract | Abstrack
Implementation of development project will run optimally when there is a good
planning. Scheduling a project can be done by described the components of the
activities to be carried out. Types of activites to be implemented arranged in the order
of actiities that must be done first.
In this paper, there are two method of scedhuling. Critical Path Method (CPM)
and Project Evaluation Review Technique (PERT). Based on the calculations that
have been done then obtained a critical path A1-B-C1-D1-E1-F1-G1-H1-I1-K1-L-N1-
P-S1-T1-U1-V1-W with total time 84 days, while the PERT method with probability
of success 97,95 % need 86 days. | en_US |
dc.language.iso | id | en_US |
dc.publisher | Universitas Sumatera Utara | en_US |
dc.title | Metode Project Evaluation and Review Technique (PERT) dan Critical Path Method (CPM) dalam Optimalisasi Penjadwalan Proyek | en_US |
dc.identifier.nim | NIM070803035 | |
dc.identifier.nidn | NIDN0003035305 | |
dc.identifier.nidn | NIDN0020056004 | |
dc.identifier.kodeprodi | KODEPRODI44201#Matematika | |
dc.description.pages | 47 Halaman | en_US |
dc.description.type | Skripsi Sarjana | en_US |