Pra Rancangan Pabrik Pembuatan Sirup Glukosa dari Ampas Tebu Menggunakan Proses Hidrolisis Enzimatis dengan Kapasitas Produksi 90.000 Ton/Tahun dan Tugas Khusus: Rancangan Keteknikan Detil Reaktor Recausticizer
View/ Open
Date
2023Author
Putri, Fachreni Dwi
Advisor(s)
Halimatuddahliana
Metadata
Show full item recordAbstract
The factory design for making glucose syrup from bagasse is designed
with a production capacity of 90,000 tons/year and operates for 330 days a year.
The main process in this factory design consists of four stages, namely the raw
material preparation stage, the pretreatment stage using the kraft process, the
glucose syrup hydrolysis and purification stage, and the cooking solution
recovery stage. The amount of bagasse needed to reach the annual production
capacity is 34,070.399 kg/hour.
A glucose syrup factory from bagasse with an enzymatic hydrolysis
process is planned to be built in Tulang Bawang Regency, Lampung Province,
with a total factory area of 10,980 m2. The planned company organizational form
is a Limited Liability Company (PT) with a line and staff organizational structure,
and a total of 179 employees.
The results of the economic analysis on this good design are as follows:
Capital Investment (CI) : Rp 2.223.967.772.190
Total Cost (TC) : Rp 1.678.754.410.846
Profit Margin (PM) : 23,94%
Break Even Point (BEP) : 28,56%
Return on Investment (ROI) : 16,91%
Return on Network (RON) : 28,18%
Pay Out Time (POT) : 5 years 11 months
Internal Rate of Return (IRR) : 16,30%
Based on the results of the analysis of the technical aspects, economic
aspects and environmental aspects, it can be concluded that the factory for the
manufacture of glucose syrup from bagasse by enzymatic hydrolysis process is
feasible to be established.