Usulan Perbaikan Tata Letak Lantai Produksi dengan Menggunakan Group Technology Layout dan Algoritma Corelap pada CV. Era Baru Panel
Abstract
CV. Era Baru Panel is a manufacturing company engaged in the processing of iron
plates into several product components with final products such as flannel boxes,
Guardrail , and PJU (Public Street Lighting) poles. This company has a common
problem, namely consumer orders are not fulfilled within the specified time. This
general problem is caused by problems with the layout of the production floor,
namely there is backtracking , cross movement , and the distance between stations
is too far. This problem can be solved by improving the layout of the production
floor using the Group Technology Layout (GTL) and the CORELAP Algorithm. This
study aims to design a production floor layout that can minimize the total moment
of movement and material handling costs, with a line efficiency rate above 75%.
The results of this study indicate a decrease in the total moment of displacement on
the production floor from 112,094 m/month to 89,390 m/month using the Group
Technology Layout and 100,114 m/month using the CORELAP Algorithm. Material
Handling costs on the production floor also decreased from Rp. 22,418,800/month
to Rp 17,878,000/month using the Group Technology Layout and Rp
22,022,800/month using the CORELAP Algorithm. By comparing the total moments
of movement and material handling costs in the actual layout , the Group
Technology Layout layout , and the CORELAP Algorithm layout , the layout using
the Group Technology Layout is the chosen proposed layout . The Line Efficiency
Rate calculation for the selected proposed layout is 79.59%, so it can be said to be
an efficient production floor layout.